Vivek SaranIndustrial Packaging Advisor
Case Study · Packaging Line Audit

3 Root Causes Found in 2 Days — Rs 22 Lakh Per Year Identified

A 2-day packaging line audit at a North India FMCG plant uncovered three distinct root causes of performance loss, totalling Rs 22 lakh per year in recoverable value.

FMCG plant2-day auditRs 22 lakh/year identified
Client identity is confidential. Industry: packaged food (FMCG). Location: North India. Operation: 3-shift, 5-line packaging department. Products: primary rigid and flexible packs, secondary carton and shrink wrap.

Why the Plant Called for an Audit

The plant manager had a clear problem: line OEE was reported at 74% but actual throughput felt lower. The maintenance team was responding to breakdowns but the same machines kept stopping. Consumable spend was rising without a clear explanation. A previous vendor review had resulted in a recommendation to replace two machines — at Rs 18 lakh capital. Before approving the spend, the plant manager asked for an independent assessment.

Audit Scope and Method

The audit covered all five packaging lines over two production shifts. Line OEE was measured directly during the audit rather than relying on self-reported data. Downtime was logged in real time by cause category. Consumable stock and purchase records were reviewed. Machine settings and maintenance logs were checked against manufacturer specifications.

Root Cause 1: OEE Measurement Error

The reported 74% OEE was inflated. The plant was measuring availability against planned production time, but not including breaks, shift changeovers and short stoppages below 5 minutes. When measured to industry standard (all time — all stoppages including microbreaks), actual OEE on the primary line was 58%. The gap between reported and actual OEE — 16 percentage points — represented Rs 9.5 lakh per year in understated production loss.

This was not deliberate misreporting. The plant simply did not have a standardised OEE measurement methodology. Introducing a proper measurement baseline was the first deliverable — because you cannot improve what you are not measuring correctly.

Root Cause 2: CIJ-Induced Line Stoppages — Wrong Ink Grade

Line 3 was stopping 4–6 times per shift for CIJ print quality issues — incomplete characters, satellite drops, nozzle clog warnings. Each stoppage averaged 8 minutes. At 5 stoppages per shift, 3 shifts, 26 days — this was 156 hours of downtime per year on one line. At a contribution of Rs 800 per minute for that line's output, this was Rs 7.5 lakh per year.

Root cause: the ink grade in use had been changed 8 months earlier to a "performance grade" recommended by the vendor's service engineer, which had higher viscosity than the original specification. The higher viscosity was incompatible with the machine's jetting system at the plant's ambient temperature. Reverting to the original specification eliminated the fault pattern within one shift of the audit — without any machine change.

Root Cause 3: Checkweigher Reject Rate 3x Above Benchmark

Line 2's checkweigher was rejecting 3.1% of packs — against a benchmark of 0.8–1.2% for this product type. At Rs 12 per pack content and 180,000 packs per month, the reject and rework cost was Rs 4.7 lakh per year in product write-off and labour.

Root cause investigation: the checkweigher was calibrated against a static weight but the filler on Line 2 had a +3g drift on the high side due to a worn dosing head. The checkweigher was correctly reading what it received — the problem was upstream. Resetting the filler dosing head reduced the reject rate to 0.9% within 3 days. No new equipment was needed.

What the Vendor Had Recommended vs What Was Actually Wrong

IssueVendor RecommendationAudit Finding
Low line throughputReplace two machines (Rs 18 lakh)OEE measurement error — no machine change required
CIJ downtime on Line 3Service contract upgrade (Rs 1.2 lakh/year)Wrong ink grade — revert to original specification
Checkweigher rejectsReplace checkweigher (Rs 6.5 lakh)Filler dosing head drift — Rs 8,000 repair

Total capital spend recommended by vendor: Rs 24.5 lakh + Rs 1.2 lakh/year. Total capital spend after independent audit: Rs 0. Total recoverable value identified: Rs 21.7 lakh per year.

18-Month Improvement Roadmap

Key takeaway: Rs 24.5 lakh of vendor-recommended capital was not needed. Rs 22 lakh per year of recoverable value was identified by a 2-day independent audit. The first year's net benefit — saving avoided capital plus recovered throughput value — was Rs 38 lakh. The audit fee was recovered in the first week of implementation.